Monday, 3 September 2012

My 26th week at Stauch & Partners Architects

In my 26th week, (6-10 August) I just went on with the bathroom layouts which were changed constantly and turns out that it took quite some time to draw up properly: which was not very exciting. :-P
I had a site visit on monday (to the site on which's drawings I'm currently working on).  We had a short site talk/ meeting. They had huge excavations going on there to lay the (reinforced concrete) stormwater pipes intended for that area. They are beneath the units and 1200mm in diameter = massive!