For two weeks we had our fifth and last Blog date (25th September to 5th October). It was great fun. So when I went back for my 33rd week (8-12 October), I just wanted to go back again. :-)
I printed out the waterproofing Details that were issued to site for construction and the sliding sunscreen drawing which was handed in for pricing.
I started drawing up changes of one of the Units garage, as well as the new entrance of the complex and two shading structures, for council submission.
I also went to site again on Wednesday. They were pretty far on the construction of Unit 5 (which is build first). The roof trusses were up and they were busy plastering the walls. I must say: exellent plaster work. As smooth as concrete. :-)